Quarterly Action Plan for the Special Project - Under SGSY


 

  Third Year        (Rs. in lacs)
S. No. Items 1st Ouarter (01.01.07 to 31.03.07) Ilnd Ouarter (01.04.07 to 30.06.07) Illrd Ouarter (01.07.07 to 30.09.07) IVth Ouarter (01.10.07 to 31.12.07) Total
    Nos. Amount Nos. Amount Nos. Amount Nos. Amoun Nos. Amount
1 Administrative Cost -- 1.67 - 1.67 - 1.68   1.67 - 6.69
2 OTHERS
  a) Postage, Telephone etc. - 0.17 - 0.18 - 0.18 - 0.17 - 0.70
b) Insurance - 1.37 - 1.38 - 1.38 - 1.37 - 5.50
c) Maintence - 0.78 - 0.78 - 0.79 - 0.80 - 3.15
d) Depreciation for Building (from third year) - 0.56 - 0.56 - 0.55 - 0.55 - 2.22
  Total (1 to 2) - 4.55 - 4.57 - 4.58 - 4.56 - 18.26
  B/F first year Total 150 46.84 150 50.84 20 13.60 - 5.89 320 117.17
  B/F Second year Total 170 43.30 170 45.30 150 42.84 150 48.35 640 179.79
 
Grand Total of Project Cost 320 94.69 320 100.71 170 61.01 150 58.80 960 315.22
 
Note

a) Training started in first quarter after receiving the F/S and funds. After completed the training implements
     to all 960 Spinners, Weavers & artizans will be distributed up to the end of 2nd year.

b)
Construction Work for sheds etc started in the first quarter of the first year as per requirements basis and
     will be completed up to end of second year.

c)
Processing Plant proposed to be established in IVth quarter of second year after completion of construction
    of sheds for the same.

d) In the third year employment as well as production work will be in full capacity and from third year
     depreciation and maintenance will be done.
 